You ask your subordinates how long it will take to complete the job they are working on.The subordinates say,"If everything goes right it will take 6 hours,most likely it will take 8 hours and if everything goes wrong it will take until the end of tomorrow or another 16 hours".Since this job is a part of a larger project you must estimate the expected time it will take to complete the job.Using the three activity time estimation procedure for CPM,what is the expected time for this job?
A) 8 hours
B) 9 hours
C) 10 hours
D) 11 hours
E) 12 hours
Correct Answer:
Verified
Q68: You have the following time and
Q69: You have just computed a Z=2.55 in
Q70: A listing of immediate predecessor activities is
Q71: A company wants to use CPM analysis
Q72: A simple project listing of five
Q74: Below are the data for a
Q75: You are working on a project that
Q76: You have determined the critical path in
Q77: If you have an optimistic time of
Q78: For an activity in a Single Time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents