Solved

You Are Working on a Project That Has 12 Activities

Question 75

Multiple Choice

You are working on a project that has 12 activities and want to perform a CPM analysis on the project.You determine the critical path consists of only five activities.You then compute the variances for the five critical path activities and these variances are 3,4,2,1 and 6 days.If the desired completion date for the project is 50 days and the expected completion date for the project is 40 days,what is the probability that the project will be completed by the desired completion date?


A) 0.99379
B) 0.99180
C) 0.99772
D) 0.91924
E) 0.67364

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents