You are working on a project that has 12 activities and want to perform a CPM analysis on the project.You determine the critical path consists of only five activities.You then compute the variances for the five critical path activities and these variances are 3,4,2,1 and 6 days.If the desired completion date for the project is 50 days and the expected completion date for the project is 40 days,what is the probability that the project will be completed by the desired completion date?
A) 0.99379
B) 0.99180
C) 0.99772
D) 0.91924
E) 0.67364
Correct Answer:
Verified
Q70: A listing of immediate predecessor activities is
Q71: A company wants to use CPM analysis
Q72: A simple project listing of five
Q73: You ask your subordinates how long it
Q74: Below are the data for a
Q76: You have determined the critical path in
Q77: If you have an optimistic time of
Q78: For an activity in a Single Time
Q79: A company must perform a maintenance
Q80: If the pessimistic duration of an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents