If you have an optimistic time of 4 weeks,a most likely time of 6 weeks and a pessimistic time of 14 weeks on an activity in a CPM managed project,what is the expected time for this activity?
A) 4 weeks
B) 5 weeks
C) 6 weeks
D) 7 weeks
E) 8 weeks
Correct Answer: