A simple project listing of five activities,their predecessors and their respective time estimates are presented below:
Using the Single Time Estimate CPM procedure,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?
A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Correct Answer:
Verified
Q67: You have just performed a Single Time
Q68: You have the following time and
Q69: You have just computed a Z=2.55 in
Q70: A listing of immediate predecessor activities is
Q71: A company wants to use CPM analysis
Q73: You ask your subordinates how long it
Q74: Below are the data for a
Q75: You are working on a project that
Q76: You have determined the critical path in
Q77: If you have an optimistic time of