Solved

Consider the Following PERT/CPM Network with Estimated Times in Weeks

Question 60

Essay

Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.  Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:  \begin{array} { c c | c c }  \text { Activity } & \text { Variance } & \text { Activity } & \text { Variance } \\ \hline \text { A } & 1.1 & \mathrm { E } & 0.3 \\ \text { B } & 0.5 & \mathrm {~F} & 0.6 \\ \text { C } & 1.2 & \mathrm { G } & 0.6 \\ \text { D } & 0.8 & \mathrm { H } & 1.0 \end{array}   a.Give the expected project completion date and the critical path. b.By what date are you 99% sure the project will be completed? The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:  Activity  Variance  Activity  Variance  A 1.1E0.3 B 0.5 F0.6 C 1.2G0.6 D 0.8H1.0\begin{array} { c c | c c } \text { Activity } & \text { Variance } & \text { Activity } & \text { Variance } \\\hline \text { A } & 1.1 & \mathrm { E } & 0.3 \\\text { B } & 0.5 & \mathrm {~F} & 0.6 \\\text { C } & 1.2 & \mathrm { G } & 0.6 \\\text { D } & 0.8 & \mathrm { H } & 1.0\end{array}
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?

Correct Answer:

verifed

Verified

a.16 weeks = Aug.21
...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents