Three Paths of a PERT Network Have These Mean Durations

Question 61

Essay

Three paths of a PERT network have these mean durations and variances in weeks:  Path  Mean  Duration  Variance 1452.752445.503461.20\begin{array} { c c c } \hline \text { Path } & \begin{array} { c } \text { Mean } \\\text { Duration }\end{array} & \text { Variance } \\\hline 1 & 45 & 2.75 \\2 & 44 & 5.50 \\3 & 46 & 1.20 \\\hline \hline\end{array} Which path offers the greatest risk of overrunning a contract deadline of 48 weeks?

Correct Answer:

verifed

Verified

Path 1: st = 1.658; z = 1.809; ...