A company finds that the residual value of $8,000 for the equipment in a capital budgeting project has been inadvertently omitted from the calculation of the net present value (NPV) for that project. How does this omission affect the NPV of that project?
A) The project's NPV should be higher, but be less than $8,000 higher, with the residual value included.
B) The project's NPV should be $8,000 higher with the residual value included.
C) The project's NPV should be $8,000 lower with the residual value included.
D) The project's NPV should be lower, but be less than $8,000 lower, with the residual value included.
Correct Answer:
Verified
Q137: The residual value is considered in a
Q138: The net present value method assumes that
Q139: The hurdle rate is the length of
Q140: When evaluating the cash flows from an
Q141: Reece Corporation is considering the purchase of
Q143: Karpets Industries is investing in a new
Q144: Ryker Manufacturing is evaluating investing in a
Q145: Byer, a plastics processor, is considering the
Q146: The Speedy-Delivery Company has two options for
Q147: The profitability index is also known as
A)future
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents