Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 12345 Gross Requirements 400500300 Scheduled receipts 00000 Projected ending Inventory 100100 Net Requirements  Planned Receipts 300 Planned Orders \begin{array} { | l | c | c | c | c | c | } \hline & 1 & 2 & 3 & 4 & 5 \\\hline \text { Gross Requirements } & & & 400 & 500 & 300 \\\hline \text { Scheduled receipts } & 0 & 0 & 0 & 0 & 0 \\\hline \text { Projected ending Inventory } & 100 & 100 & & & \\\hline \text { Net Requirements } & & & & & \\\hline \text { Planned Receipts } & & & 300 & & \\\hline \text { Planned Orders } & & & & & \\\hline\end{array}


A) 200
B) 300
C) 400
D) 500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents