There is no beginning inventory. What are the net requirements in week 4 if there is a scheduled receipt of 100 units each week and a two week production lead time?
A) 250
B) 300
C) 350
D) 400
Correct Answer:
Verified
Q44: MRP is NOT capable of:
A)lowering inventory levels.
B)helping