The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities
Correct Answer:
Verified
Q5: A Gantt chart of a project shows
Q6: Projects involve routine activities that are performed
Q7: The earliest finish time for an activity
Q8: The activities with the longest durations in
Q11: In PERT,the project duration will never exceed
Q12: The length of the critical path is
Q13: Project managers must often function in an
Q14: An activity in a project network cannot
Q15: The earliest start of an activity is
Q55: In PERT, the path with the fewest