An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days The expected duration of this activity is:
A) 7 0 days
B) 7 5 days
C) 8 0 days
D) 8 5 days
E) 10 0 days
Correct Answer:
Verified
Q59: The duration of the critical path is:
A)11
Q65: Activity C in a project network has
Q66: There are four activities on the critical
Q67: The standard deviation of a path is
Q68: The path with the greatest slack is:
A)A-E-H
Q79: Activity C has an early start time
Q84: What is the estimated slack time for
Q86: What is the probability that this project
Q89: What is the estimated standard deviation in
Q96: The expected duration of this project is:
A)13
B)15
C)20
D)52
E)81