The standard deviation of a path is computed as:
A) the sum of the standard deviations of all activities on the path
B) the square root of the sum of the standard deviations of all activities on the path
C) the sum of the variances of all activities on the path
D) the square root of the sum of the variances of all activities on the path
E) None of the above
Correct Answer:
Verified
Q64: An activity has an optimistic time estimate
Q65: Activity C in a project network has
Q66: There are four activities on the critical
Q68: The path with the greatest slack is:
A)A-E-H
Q70: The slack for path A-D-H-I is:
A)0
B)3
Q71: There are four activities on the critical
Q72: What is the estimated mean time for
Q84: What is the estimated slack time for
Q89: What is the estimated standard deviation in
Q96: The expected duration of this project is:
A)13
B)15
C)20
D)52
E)81
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents