There are four activities on the critical path Coincidentally,their standard deviations are all equal to 4 The standard deviation of the critical path is therefore equal to:
A) 2 days
B) 4 days
C) 8 days
D) 16 days
E) 64 days
Correct Answer:
Verified
Q66: There are four activities on the critical
Q67: The standard deviation of a path is
Q68: The path with the greatest slack is:
A)A-E-H
Q70: The slack for path A-D-H-I is:
A)0
B)3
Q72: What is the estimated mean time for
Q73: When finding the approximate probability of project
Q76: An important assumption in PERT calculations is:
A)activity
Q84: What is the estimated slack time for
Q105: What is the estimated standard deviation in
Q109: What is the estimated slack time for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents