There Are Four Activities on the Critical Path Coincidentally,their Standard

Question 71

Multiple Choice

There are four activities on the critical path Coincidentally,their standard deviations are all equal to 4 The standard deviation of the critical path is therefore equal to:


A) 2 days
B) 4 days
C) 8 days
D) 16 days
E) 64 days