When finding the approximate probability of project duration,it is necessary to know which of the following?
A) The mean and variance of each activity
B) The mean of each activity on the critical path
C) The standard deviation of only the activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity times
Correct Answer:
Verified
Q68: The path with the greatest slack is:
A)A-E-H
Q70: The slack for path A-D-H-I is:
A)0
B)3
Q71: There are four activities on the critical
Q72: What is the estimated mean time for
Q76: An important assumption in PERT calculations is:
A)activity
Q77:
-What is the estimated mean time
Q78:
-What is the estimated mean time
Q84: What is the estimated slack time for
Q105: What is the estimated standard deviation in
Q109: What is the estimated slack time for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents