An important assumption in PERT calculations is:
A) activity durations are normally distributed
B) activity durations are independent
C) a computer will be available to do the calculations
D) a and b only
E) a and c only
Correct Answer:
Verified
Q71: There are four activities on the critical
Q72: What is the estimated mean time for
Q73: When finding the approximate probability of project
Q77:
-What is the estimated mean time
Q78:
-What is the estimated mean time
Q79: What is the estimated mean time for
Q80: The critical path for the network shown
Q81: Which of the following are ways of
Q105: What is the estimated standard deviation in
Q109: What is the estimated slack time for