What is the estimated mean time for activity E?
A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days
Correct Answer:
Verified
Q67: The standard deviation of a path is
Q68: The path with the greatest slack is:
A)A-E-H
Q70: The slack for path A-D-H-I is:
A)0
B)3
Q71: There are four activities on the critical
Q73: When finding the approximate probability of project
Q76: An important assumption in PERT calculations is:
A)activity
Q77:
-What is the estimated mean time
Q84: What is the estimated slack time for
Q105: What is the estimated standard deviation in
Q109: What is the estimated slack time for