Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days Its expected duration is approximately:
A) 5 days
B) 6 days
C) 7 days
D) 8 days
E) 9 days
Correct Answer:
Verified
Q64: An activity has an optimistic time estimate
Q66: There are four activities on the critical
Q67: The standard deviation of a path is
Q68: The path with the greatest slack is:
A)A-E-H
Q70: The slack for path A-D-H-I is:
A)0
B)3
Q79: Activity C has an early start time
Q84: What is the estimated slack time for
Q86: What is the probability that this project
Q89: What is the estimated standard deviation in
Q96: The expected duration of this project is:
A)13
B)15
C)20
D)52
E)81