The eleven tasks necessary to assemble an MP3 player along with their time (in seconds) and immediate predecessor(s) is given below:
The company wants to produce 600 units in a 9-hour day.
-The minimum number of workstations required is _____.
A) 5
B) 6
C) 7
D) 8
Correct Answer:
Verified