A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc. The desired output rate of 30 spreaders per hour will be achieved. The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled. Which of the following statements is TRUE?
A) The cycle time is 30 seconds per spreader.
B) The theoretical minimum number of workstations is 10.
C) If the solution calls for 12 stations, the efficiency is 90%.
D) If the solution calls for 11 stations, the efficiency is 80%.
Correct Answer:
Verified
Q23: Which of the following is NOT an
Q24: Consider the following assembly line information
Q25: An assembly line with 28 activities is
Q26: Consider the following assembly line information
Q27: Assembly-Line Balancing Problem-Table 1 below
The Florida
Q29: The eleven tasks necessary to assemble
Q30: An assembly line with 28 activities is
Q31: A(n) _ team performs entire jobs rather
Q32: For a given cycle time in line
Q33: Which of the following statements is NOT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents