An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 88 minutes. The longest activity is 2.2 minutes and the shortest is 0.8 minutes. The line will operate for 450 minutes per day. Using a cycle time of 60 seconds, determine an assembly-line balance by selecting the longest-processing-time task available. Compute the total idle time and assembly-line efficiency.
-The total idle time is _____ seconds.
A) less than or equal to 20
B) more than 20 but less than or equal to 30
C) more than 30 but less than or equal to 40
D) more than 40 but less than or equal to 50
Correct Answer:
Verified
Q25: An assembly line with 28 activities is
Q26: Consider the following assembly line information
Q27: Assembly-Line Balancing Problem-Table 1 below
The Florida
Q28: A line-balancing solution has been developed for
Q29: The eleven tasks necessary to assemble
Q31: A(n) _ team performs entire jobs rather
Q32: For a given cycle time in line
Q33: Which of the following statements is NOT
Q34: An assembly line with 28 activities is
Q35: _ is vertical expansion of job duties
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents