An electronics company wants to develop an MRP schedule for one of its key components, a specialized chip. The lot size is 600, the lead time is 2 weeks, there are 900 units on hand with 300 of those as safety stock and 500 already allocated. There are gross requirements for 2000 units in Week 3 and 1500 units in Week 5. There are 600 units scheduled to be received in Week 1.
a.What is the number of units available in Week 3?
b.What is the planned order receipt for Week 5?
Correct Answer:
Verified
Q86: A special project in a manufacturing
Q87: A manufacturing company is trying to
Q88: The Eugene plant of Basic Computers Inc.
Q89: A company that makes inkjet printers is
Q90: The Pacific Chemical Company produces high
Q92: It is time for a company
Q93: A company currently has no items in
Q94: A sheet metal company has developed
Q95: A company makes traffic signals for downtown
Q96: What is capacity requirements planning (CRP)?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents