A company that makes inkjet printers is trying to determine a MRP schedule for the print cartridges it needs in its newest model of printer. They have gross requirements of 1000 units in week 2 and 900 units in week 4. The minimum lot size is 500 units and the lead time is 1 week. They currently have 300 units on hand that includes a safety stock of 150 and another 100 units already allocated. They have 500 units scheduled for receipt in week 1.
a.What is the number of units available in Week 1?
b.What is the planned order release in Week 3?
Correct Answer:
Verified
Q84: A company assembles microcomputers for sale
Q85: Explain the three lot sizing methods, and
Q86: A special project in a manufacturing
Q87: A manufacturing company is trying to
Q88: The Eugene plant of Basic Computers Inc.
Q90: The Pacific Chemical Company produces high
Q91: An electronics company wants to develop an
Q92: It is time for a company
Q93: A company currently has no items in
Q94: A sheet metal company has developed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents