A special project in a manufacturing company has the following master production schedule (MPS) for the next eight weeks:
 Week 12345678 Units 7506258009251000900675675\begin{array} { | l | l | l | l | l | l | l | l | l | } \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\\hline \text { Units } & 750 & 625 & 800 & 925 & 1000 & 900 & 675 & 675 \\\hline\end{array} The weekly fabrication and welding capacity (in hours) available and production standards (in hours per unit) are:
 Fabrication  Welding  Capacity Available 7,50010,000 Production Standard 811\begin{array}{|l|l|l|}\hline & \text { Fabrication } & \text { Welding } \\\hline \text { Capacity Available } & 7,500 & 10,000 \\\hline \text { Production Standard } & 8 & 11 \\\hline\end{array}
a.What is the percentage utilization of the fabrication capacity in Week 5?
b.What is the percentage utilization of the welding capacity in Week 2?
c.In which weeks are the welding area requirements over capacity?

Correct Answer:

verifed

Verified

a. 106.7; ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents