Solved

A High Definition Television Manufacturer in Asia Wants to Develop

Question 79

Multiple Choice

A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions
-The expected duration of the critical path in days is _____.


A) less than or equal to 20 days
B) greater than 20 but less than or equal to 25 days
C) greater than 25 but less than or equal to 30 days
D) greater than 30 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents