You Are in Charge of the "Advertising Program" for the Boston

Question 101

Essay

You are in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season.  Activity  Immediate Predecessor(s)  Activity Time (weeks)  A  none 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D E 2\begin{array}{lcl}\text { Activity }&\text { Immediate Predecessor(s) }&\text { Activity Time (weeks) }\\\hline\text { A } & \text { none } & 1 \\\text { B } & \text { A } & 2 \\\text { C } & \text { A } & 3 \\\text { D } & \text { A, B } & 4 \\\text { E } & \text { C, D } & 3 \\\text { F } & \text { D E } & 2\end{array}
a.What is the earliest completion time for this project?
b.What is the largest amount of slack that any activity has in this project?
c.If activity C is delayed by three weeks, what is the revised earliest project completion time?
d.For the original Critical Path Method problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks, assuming all activity crash costs per week are the same and all activities can be crashed?

Correct Answer:

verifed

Verified

a.12 weeks...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents