Consider the Project Network and Data Shown Below ADetermine the Critical Path and the Project Completion Time

Question 104

Essay

Consider the project network and data shown below:  Consider the project network and data shown below:    \begin{array}{|c|c|c|c|c|c|c|} \hline\text { Activity } & \text { Slack } & \begin{array}{c} \text { Normal } \\ \text { Time } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Time } \end{array} & \begin{array}{c} \text { Normal } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash } \\ \text { Cost } \end{array} & \begin{array}{c} \text { Crash Cost } \\ \text { Per Week } \end{array} \\ \hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\ \hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\ \hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\ \hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\ \hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\ \hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\ \hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\ \hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\ \hline \end{array}   a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?  Activity  Slack  Normal  Time  Crash  Time  Normal  Cost  Crash  Cost  Crash Cost  Per Week  A 074$400$750B1129$1,000$2,200C076$800$1,100D065$600$1,000E086$1,200$2,200F932$800$1,000G932$500$650H043$400$600I065$900$1,300\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Activity } & \text { Slack } & \begin{array}{c}\text { Normal } \\\text { Time }\end{array} & \begin{array}{c}\text { Crash } \\\text { Time }\end{array} & \begin{array}{c}\text { Normal } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash } \\\text { Cost }\end{array} & \begin{array}{c}\text { Crash Cost } \\\text { Per Week }\end{array} \\\hline \text { A } & 0 & 7 & 4 & \$ 400 & \$ 750 & \\\hline \mathrm{B} & 1 & 12 & 9 & \$ 1,000 & \$ 2,200 & \\\hline \mathrm{C} & 0 & 7 & 6 & \$ 800 & \$ 1,100 & \\\hline \mathrm{D} & 0 & 6 & 5 & \$ 600 & \$ 1,000 & \\\hline \mathrm{E} & 0 & 8 & 6 & \$ 1,200 & \$ 2,200 & \\\hline \mathrm{F} & 9 & 3 & 2 & \$ 800 & \$ 1,000 & \\\hline \mathrm{G} & 9 & 3 & 2 & \$ 500 & \$ 650 & \\\hline \mathrm{H} & 0 & 4 & 3 & \$ 400 & \$ 600 & \\\hline \mathrm{I} & 0 & 6 & 5 & \$ 900 & \$ 1,300 & \\\hline\end{array}
a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?

Correct Answer:

verifed

Verified

a. The critical path consists of activit...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents