Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A-D-H-I-J-K.
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
Correct Answer:
Verified
Q97: Describe how a project fits into each
Q98: Using a beta probability distribution to characterize
Q99: Define critical path and explain how it
Q100: Explain the role of project managers and
Q101: You are in charge of the
Q103: The following network shows all the
Q104: Consider the project network and data
Q105: Consider the project network and data
Q106: You are responsible for managing an
Q107: The network below represents a project being
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents