Solved

The Project Team Toiled Long into the Night to Develop

Question 53

Multiple Choice

The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below.What is the overall risk factor for the project?  Maturity 0.7 Cost 0.4 Complexity 0.6 Schedule 0.6 Dependency 0.8 Reliability 0.8 Performance 0.9\begin{array} { | l | l | l | l | } \hline \text { Maturity } & 0.7 & \text { Cost } & 0.4 \\\hline \text { Complexity } & 0.6 & \text { Schedule } & 0.6 \\\hline \text { Dependency } & 0.8 & \text { Reliability } & 0.8 \\\hline & & \text { Performance } & 0.9 \\\hline\end{array}


A) Less than or equal to 0.7
B) Greater than 0.7 but less than or equal to 0.8
C) Greater than 0.8 but less than or equal to 0.9
D) Greater than 0.9

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents