A manufacturing company wants to accelerate a project it has underway for a new product in order to beat their competitors to market. They used CPM to develop the project which has the following activities, durations in weeks), costs in dollars), and precedence relationships:
a. How many paths are in the network?
b. What is the latest finish (LF) time for activity g?
c. What is the slack in weeks for activity c?
d. What is the critical path for this project?
e. What is the duration of the critical path in weeks
f. What activity should be crashed first in order to accelerate the project
g. What is the final project duration in weeks assuming it is crashed as far as possible
h. What is total cost to crash the project as far as possible?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q52: Explain the stages of the project life
Q58: Data regarding the activities for a
Q59: A company wants to develop a
Q61: A company has developed a project
Q62: A company has used PERT for
Q63: You are responsible for managing an
Q64: You are in charge of the
Q81: Describe the four major steps in the
Q83: List at least six principal factors (contributors)
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents