In making a forward pass through a network, three activities are immediate predecessors for activity T. What is the early start time for activity T?
A) the smallest ES for the three activities that are immediate predecessors for activity T
B) the largest ES for the three activities that are immediate predecessors for activity T
C) the smallest EF for the three activities that are immediate predecessors for activity T
D) the largest EF for the three activities that are immediate predecessors for activity T
E) the activity time for activity T
Correct Answer:
Verified
Q18: The critical path is the sequential path
Q19: Which phase in the project life cycle
Q20: Which phase in the project life cycle
Q21: In making a backward pass through a
Q22: In critical path scheduling, slack is computed
Q24: Which of the following can be calculated
Q25: In making a forward pass through a
Q26: Given this information about an activity: ES
Q27: The process of calculating LS and LF
Q28: We use _ time estimates when we
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents