In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early start time for activity T?
A) 17
B) 24
C) 27
D) 33
E) 40
Correct Answer:
Verified
Q20: Which phase in the project life cycle
Q21: In making a backward pass through a
Q22: In critical path scheduling, slack is computed
Q23: In making a forward pass through a
Q24: Which of the following can be calculated
Q26: Given this information about an activity: ES
Q27: The process of calculating LS and LF
Q28: We use _ time estimates when we
Q29: With probabilistic time estimates for activities, (o)
Q30: Given this information about an activity: ES
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents