In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?
A) 13
B) 17
C) 22
D) 33
E) 37
Correct Answer:
Verified
Q16: Project managers use network planning techniques to
Q17: Which phase in the project life cycle
Q18: The critical path is the sequential path
Q19: Which phase in the project life cycle
Q20: Which phase in the project life cycle
Q22: In critical path scheduling, slack is computed
Q23: In making a forward pass through a
Q24: Which of the following can be calculated
Q25: In making a forward pass through a
Q26: Given this information about an activity: ES
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents