You cannot miss an important constraint if you apply the resource calendar to each activity to make sure the people and equipment are available on those dates.
Correct Answer:
Verified
Q24: Which of the following is true about
Q25: Resource calendars become important tools when:
A) resources
Q26: Complex projects require software that can track
Q27: When the scope of the project is
Q28: Project managers can divert some resources from
Q30: The process of deriving conclusions based on
Q31: The process for developing the project logic
Q32: An) _ has no duration or resources,
Q33: To consider the availability of team members,
Q34: The most detailed versions of the schedule
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents