Which of the following is true about estimations of activity durations?
A) The person responsible for the work will most likely exclude extra time.
B) The person with the most knowledge is the most objective person to provide duration estimates.
C) The larger and more complex the project, the greater the need for detail, which usually translates into longer durations for activities.
D) Multiple inputs into the duration estimate increase bias.
E) The accuracy of an estimate is related to the quality of the knowledge and how that knowledge is applied.
Correct Answer:
Verified
Q19: A WBS can be decomposed, that is,
Q20: People recognize patterns more effectively when they
Q21: The project work breakdown structure WBS):
A) developed
Q22: The _ is the development of the
Q23: Work performed on the project that consumes
Q25: Resource calendars become important tools when:
A) resources
Q26: Complex projects require software that can track
Q27: When the scope of the project is
Q28: Project managers can divert some resources from
Q29: You cannot miss an important constraint if
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents