Solved

Which of the Following Is True About Estimations of Activity

Question 24

Multiple Choice

Which of the following is true about estimations of activity durations?


A) The person responsible for the work will most likely exclude extra time.
B) The person with the most knowledge is the most objective person to provide duration estimates.
C) The larger and more complex the project, the greater the need for detail, which usually translates into longer durations for activities.
D) Multiple inputs into the duration estimate increase bias.
E) The accuracy of an estimate is related to the quality of the knowledge and how that knowledge is applied.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents