Question 27

Multiple Choice

When the scope of the project is being determined, a _____ schedule that shows the major tasks and approximate start and end dates is developed to allow senior management to make decisions about the scope of the project stockholders.


A) milestone
B) master
C) conceptual
D) procurement
E) specific

Correct Answer: