Which Description Best Fits a Work Breakdown Structure (WBS)

Question 11

Multiple Choice

Which description best fits a work breakdown structure (WBS) ?


A) A project planning software program is selected for use by the steering committee to assist in planning needed changes.
B) The implementation committee learns about the capabilities of a new wireless system.
C) A timeline is developed to determine who will do necessary tasks for the implementation of each project phase.
D) A committee is formed to guide the implementation of a new wireless system.

Correct Answer: