Activities following a node
A) can begin as soon as any activity preceding the node has been completed.
B) have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
C) have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
D) None of these are correct.
Correct Answer:
Verified
Q20: The length of time an activity can
Q21: Arcs in a project network indicate
A)completion times.
B)precedence
Q22: The main difference between CPM and PERT
Q23: PERT and CPM
A)are most valuable when a
Q24: When activity times are uncertain,
A)we assume they
Q26: A critical activity is
A)an activity that consumes
Q27: Activities K,M,and S immediately follow activity H,and
Q28: Activities with zero slack
A)can be delayed.
B)must be
Q29: In deciding which activities to crash,one must
Q30: Slack equals
A)LF - EF.
B)EF - LF.
C)EF -
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents