The main difference between CPM and PERT is
A) CPM and PERT use different activity time estimates.
B) PERT analysis is less expensive to conduct.
C) PERT lends itself to computerization while CPM networks must be constructed manually.
D) CPM integrates time and cost performance while PERT is based solely on time performance.
Correct Answer:
Verified
Q17: The latest finish time for an activity
Q18: A path through a project network must
Q19: A critical activity can be part of
Q20: The length of time an activity can
Q21: Arcs in a project network indicate
A)completion times.
B)precedence
Q23: PERT and CPM
A)are most valuable when a
Q24: When activity times are uncertain,
A)we assume they
Q25: Activities following a node
A)can begin as soon
Q26: A critical activity is
A)an activity that consumes
Q27: Activities K,M,and S immediately follow activity H,and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents