When activity times are uncertain,
A) we assume they are normally distributed.
B) we start by calculating the optimistic,the most probable,and the pessimistic time estimates.
C) we use the most probable time.
D) we need to obtain at least four time estimates for each activity.
Correct Answer:
Verified
Q19: A critical activity can be part of
Q20: The length of time an activity can
Q21: Arcs in a project network indicate
A)completion times.
B)precedence
Q22: The main difference between CPM and PERT
Q23: PERT and CPM
A)are most valuable when a
Q25: Activities following a node
A)can begin as soon
Q26: A critical activity is
A)an activity that consumes
Q27: Activities K,M,and S immediately follow activity H,and
Q28: Activities with zero slack
A)can be delayed.
B)must be
Q29: In deciding which activities to crash,one must
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents