In CPM,for activities with more than one immediate predecessor activity,which of the following is used to compute its earliest finish (EF) time
A) largest EF among the immediate predecessors
B) smallest LF among the immediate predecessors
C) smallest EF among the immediate predecessors
D) average of EFs among the immediate predecessors
Correct Answer:
Verified
Q48: Given the following network with activities
Q49: From this PERT/CPM network,determine the list of
Q50: The critical path for this network
Q51: Use the following network of related
Q52: A project network is shown below.Use a
Q53: From this schedule of activities,draw the
Q54: A senior MIS design class project team
Q55: Consider the following PERT/CPM network with
Q58: A project network is shown below.Use a
Q59: The main difference between CPM and PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents