Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.
The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?
Correct Answer:
Verified
a. 16 weeks = Aug...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q48: Given the following network with activities
Q49: From this PERT/CPM network,determine the list of
Q50: The critical path for this network
Q51: Use the following network of related
Q52: A project network is shown below.Use a
Q53: From this schedule of activities,draw the
Q54: A senior MIS design class project team
Q56: In CPM,for activities with more than one
Q58: A project network is shown below.Use a
Q59: The main difference between CPM and PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents