Each R requires 2 of component S and 1 of part T. The lead time for assembly of R is 3 days. The lead time for the manufacture of S is 5 days. The lead time for the manufacture of T is 10 days. The cumulative lead time for R is ________ days.
A) 6
B) 9
C) 13
D) 17
E) 22
Correct Answer:
Verified