Free slack is the amount of time a specific activity can be
A) postponed without delaying the earliest start time of its immediately preceding activities.
B) postponed without delaying the earliest start time of its immediately succeeding activities.
C) accelerated without delaying the latest start time of its immediately succeeding activities.
D) accelerated without delaying the latest finish time of its immediately preceding activities.
Correct Answer:
Verified
Q65: With respect to the project schedule, changes
Q66: As the project progresses, the actual finish
Q67: If the planned corrective actions do not
Q68: The estimated duration for each activity is
Q69: The total completion time is 25 days.Task
Q71: The key to effective project control is
Q72: A concentrated effort to accelerate project progress
Q73: Eliminating negative slack by reducing durations of
Q74: Total slack is calculated for each of
Q75: Schedule control involves four steps.List the four
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents