The Key to Effective Project Control Is Measuring Actual Progress

Question 71

Multiple Choice

The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and


A) taking any needed corrective action immediately.
B) leaving the project to self-correct.
C) fast tracking all the activities in the project until the project is ahead of schedule.
D) making sure the critical path doesn't change.

Correct Answer: