The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.How much slack does the project have now that Task A is finished?
A) Negative 5 days slack.
B) Positive 5 days slack.
C) Positive 16 days slack.
D) Positive 3 days slack.
Correct Answer:
Verified
Q64: Schedule control involves four steps.Place these steps
Q65: With respect to the project schedule, changes
Q66: As the project progresses, the actual finish
Q67: If the planned corrective actions do not
Q68: The estimated duration for each activity is
Q70: Free slack is the amount of time
Q71: The key to effective project control is
Q72: A concentrated effort to accelerate project progress
Q73: Eliminating negative slack by reducing durations of
Q74: Total slack is calculated for each of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents