Solved

As the Project Progresses, the Actual Finish Times (AFs)of Completed

Question 66

Multiple Choice

As the project progresses, the actual finish times (AFs) of completed activities will determine


A) the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
B) the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack.
C) the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack.
D) the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents