As the project progresses, the actual finish times (AFs) of completed activities will determine
A) the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
B) the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack.
C) the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack.
D) the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack.
Correct Answer:
Verified
Q61: Free slack is calculated by finding the
Q62: Analyzing the schedule to determine which areas
Q63: The total completion time is 25 days.Task
Q64: Schedule control involves four steps.Place these steps
Q65: With respect to the project schedule, changes
Q67: If the planned corrective actions do not
Q68: The estimated duration for each activity is
Q69: The total completion time is 25 days.Task
Q70: Free slack is the amount of time
Q71: The key to effective project control is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents