A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 300 units per day. The tasks necessary to produce this product are detailed in the table below.
(a) Draw the network described in the table.
(b) Without regard to a production schedule, what is the minimum possible cycle time (in seconds) for this situation; what is the maximum?
(c) What is the required cycle time (in seconds) in order to meet the schedule?
(d) What is the theoretical minimum number of workstations needed to meet the schedule?
(e) Balance this line using longest processing time.
(f) What is the efficiency of the balance obtained in part e?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q297: A production line is to be designed
Q298: A production line is to be designed
Q299: Which of the following is one of
Q300: A production line is to be designed
Q301: Explain what the purpose of assembly-line balancing
Q303: Cyclone Appliances has developed a new European-style
Q304: An assembly line has been designed to
Q305: An electronics manufacturer makes remote control devices
Q306: A facility is trying to set up
Q307: Assembly line balancing has just been used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents