Question 301
Multiple Choice
Which of the following tasks are responsibilities of the project manager role?
Question 302
Multiple Choice
Which of the following are the roles involved in a Scrum project?
Question 303
Multiple Choice
Ann, a project manager, is working for a new company. On her first project, the assigned project resources do not follow her direction. She is not allowed to authorize contractors because they say she does not have the authority. Which of the following is the MOST likely explanation for what is happening?
Question 304
Multiple Choice
A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?
Question 305
Multiple Choice
The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
Question 306
Multiple Choice
Risk ID 2 has occurred.
Which of the following ways should the project manager update the risk register?
Question 307
Multiple Choice
Which of the following provides tools and standard documentation for the project team?
Question 308
Multiple Choice
A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:
Question 309
Multiple Choice
Which of the following should a project manager consider as part of a make or buy analysis?
Question 310
Multiple Choice
A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?
Question 311
Multiple Choice
A project manager is reviewing project performance. Which of the following would be the BEST indicator of the total project cost?
Question 312
Multiple Choice
The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)
Question 313
Multiple Choice
A company purchased a parachute supplier and is now sending parachutes to the research and development department. Which of the following has occurred?
Question 314
Multiple Choice
A company was originally organized using a functional structure; however, the company has decided to go forward with a matrix structure to get the most utilization of resources. This is an example of:
Question 315
Multiple Choice
The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?
Question 316
Multiple Choice
According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site. From the stakeholders' point of view, accessing the weekly report is an example of: