Question 441
Multiple Choice
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?
Question 442
Multiple Choice
A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding actions to take. Which of the following activities does this describe?
Question 443
Multiple Choice
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
Question 444
Multiple Choice
Which of the following will identify the MOST potential project risks?
Question 445
Multiple Choice
Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
Question 446
Multiple Choice
A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
Question 447
Multiple Choice
A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?
Question 448
Multiple Choice
A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.)