Question 81
Multiple Choice
A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?
Question 82
Multiple Choice
The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?
Question 83
Multiple Choice
Using Scrum, which of the following are discussed in a daily standup meeting?
Question 84
Multiple Choice
A project team on a four-year project has a shortage of workspace within an office. Which of the following is the MOST viable solution for the project team while ensuring work hours are not wasted?
Question 85
Multiple Choice
A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?
Question 86
Multiple Choice
A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
Question 87
Multiple Choice
Which of the following charts is a graphical representation of the causes of a specific event?
Question 88
Multiple Choice
A team member has completed an assigned task. Which of the following roles should be notified FIRST?
Question 89
Multiple Choice
? new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
Question 90
Multiple Choice
The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
Question 91
Multiple Choice
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:
Question 92
Multiple Choice
Which of the following would indicate a project manager is working in a matrix-based organization?
Question 93
Multiple Choice
A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?
Question 94
Multiple Choice
A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?
Question 95
Multiple Choice
A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
Question 96
Multiple Choice
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
Question 97
Multiple Choice
A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?
Question 98
Multiple Choice
A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the MOST likely reason for the failed inspection?
Question 99
Multiple Choice
At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?